5.
When the XNX completes boot-up, perform a Soft Reset on the Excel from
the Calibration Menu.
6.
When the reset is complete, Set Date & Time.
7.
Set the Path Length for the application, then align the transmitter and
receiver with Align Excel.
8.
Once the alignment is complete, a Zero Calibration must be performed on
the Excel to complete the commissioning process. (See the Searchline Excel
Technical Manual for calibration information P/N 2104M0506).
9.
Reset any faults displayed on the XNX display. The XNX and Excel are
now ready to monitor.