Step 3: Unpack The Switch - NETGEAR XS728T Hardware Installation Manual

Prosafe 28-port and 48-port 10-gigabit smart managed switch
Hide thumbs Also See for XS728T:
Table of Contents

Advertisement

ProSAFE 28-Port and 48-Port 10-Gigabit Smart Managed Switch Models XS728T and XS748T
Handle all sensitive components in a static-safe area. If possible, use antistatic floor pads,
workbench pads, and an antistatic grounding strap.

Step 3: Unpack the Switch

The following figure shows the package contents of the switch.
Figure 8. Package contents (model XS748T shown)
Check the contents of the boxes to make sure that all items are present before installing the
switch.
To check the package contents:
1.
Place the container on a clean flat surface, and cut all straps securing the container.
2.
Unpack the hardware from the box by carefully removing the hardware and placing it on a
secure and clean surface.
3.
Remove all packing material.
4.
Verify that the package contains the following items:
Model XS728T or Model XS748T Smart Managed Switch
AC power cord (localized to the country of sale)
19-inch rack-mount kit for rack installation
Rubber footpads for tabletop installation
Installation guide
Resource CD with NETGEAR Smart Control Center
If any item is missing or damaged, contact the place of purchase immediately.
Installation
24

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Xs748t

Table of Contents