8 Commissioning

8.1 Establishing a Connection to Sunny Portal

Requirements:
☐ DHCP must be activated on the router (see router manual). If your router does not support
DHCP, you can configure the static network settings on the Sunny Home Manager using the
Sunny Home Manager Assistant (see Section 9.4, page 62).
☐ The Sunny Home Manager must be connected to the router (see Section 7.4, page 41).
☐ The Sunny Home Manager must be supplied with voltage (see Section 7.6, page 42).
The Sunny Home Manager automatically establishes a connection to Sunny Portal. As soon as the
status LED is intermittently flashing green and orange (after approximately two minutes), you can
register the Sunny Home Manager in Sunny Portal (see Section 8.2, page 45).
If the status LED is continuously flashing red, the Sunny Home Manager cannot automatically
establish the connection to Sunny Portal. This is the case, for example, if there is a proxy server in your
network or if your router does not support DHCP.
• If the status LED is continuously flashing red or you have to manually configure the IP address
in your network, use the Sunny Home Manager Assistant (see Section 9.4, page 62).

8.2 Registering in Sunny Portal

Sunny Portal is the user interface of the Sunny Home Manager. Therefore, you must register the
Sunny Home Manager in Sunny Portal.
Requirements:
☐ The status LED of the Sunny Home Manager must be intermittently flashing green and orange
(see Section 8.1 "Establishing a Connection to Sunny Portal", page 45).
☐ The PV system must be in operation.
– The same NetID must be set for all BLUETOOTH devices.
– The BLUETOOTH PV system must be in operation.
– The Speedwire devices must be in operation and connected to the Sunny Home Manager
via a router/network switch.
– NetID 0 must be set for Speedwire devices with integrated BLUETOOTH interface.
Procedure
• Start the PV System Setup Assistant.
• Register as a new user in the Sunny Portal.
or
Log in to Sunny Portal as an existing user.
• Register Sunny Home Manager system in Sunny Portal.
• Configure the energy meter.
• Enter the PV system data.