INSTALLATION - GAS BOOSTED SYSTEMS

GAS BOOSTER CLEARANCES

Figure 6.2 from AS/NZS5601 is reproduced below. It was current at the time of printing, but may have been
superseded. It is the installer's responsibility to ensure that current requirements are met.
Flue terminal
Ref.
Below eaves, balconies and other projections:
a
• Appliances up to 50 MJ/h input
• Appliances over 50 MJ/h input
b
From the ground, above a balcony or other surface *
c
Front a return wall or external corner *
From a gas meter (M) (see 5.11.5.9 for vent terminal location of regulator )
d
(see Table 6.6 for New Zealand requirements)
e
From an electricity meter or fuse box (P) †
f
From a drain pipe or soil pipe
g
Horizontally from any building structure* = or obstruction facing a terminal
h
From any other flue terminal , cowl, or combustion air intake †
Horizontally from an openable window, door, non-mechanical air inlet, or any other opening into a building
with the exception of sub-floor ventilation:
• Appliances up to 150 MJ/h input *
• Appliances over 150 MJ/h input up to 200 MJ/h input *
j
• Appliances over 200 MJ/h input up to 250 MJ/h input *
• Appliances over 250 MJ/h input *
• All fan-assisted flue appliances , in the direction of discharge
k
From a mechanical air inlet, including a spa blower
Vertically below an openable window, non-mechanical air inlet, or any other opening into a building with the
exception of sub-floor ventilation:
• Space heaters up to 50 MJ/h input
n
• Other appliances up to 50 MJ/h input
• Appliances over 50 MJ/h input and up to 150 MJ/h input
• Appliances over 150 MJ/h input
* - unless appliance is certified for closer installation
† - Prohibited area below electricity meter or fuse box extends to ground level.
NOTES:
1
Where dimensions c, j or k cannot be achieved an equivalent horizontal distance
measured diagonally from the nearest discharge point of the terminal to the opening
may be deemed by the Technical Regulator to comply.
2
See Clause 6.9.4 for restrictions on a flue terminal under a covered area.
3
See Figure J3 for clearances required from a flue terminal to an LP Gas cylinder.
A flue terminal is considered to be a source of ignition.
4
For appliance s not addressed above acceptance should be obtained from the Technical Regulator.
EXTRACT OF FIGURE 6.2 (in-part)
Rinnai
Fan assisted flue appliance only
Item
Gas meter
Electricity meter or fuse box
Min. clearances (mm)
36
Mechanical air inlet
Fan assisted
200
300
300
300
1000
500
75
500
300
300
300
500
1500
1500
1000
150
500
1000
1500
Split Solar OIM

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

EquinoxSunmaster

Table of Contents