Clutches With 8 Hex Socket Bolts; Clutch Run-In; Clutch Disassembly & Assembly; Shearbolt Protection - Land Pride RTR15 Operator's Manual

Rotary tillers rtr10 & rtr15 series
Hide thumbs Also See for RTR15:
Table of Contents

Advertisement

Land Pride
Section 4: Maintenance & Lubrication

Clutches With 8 Hex Socket Bolts

Clutch Run-In

Refer to Figure 4-3 on page 25:
1. Loosen counterclockwise all 8 hex head socket bolts
uniformly 6 full turns.
2. Cycle clutch on and off 5 or 6 times (15 seconds on
and 15 seconds off) with the engine operating at half
throttle. Disengage driveline, shut off tractor and
remove key. Wait for all components to stop before
dismounting from tractor.
3. Tighten hex head socket bolts fully back. Clutch is
ready for use
4. The clutch should be checked during the first hour of
cutting and periodically each week.
Hex Head
Socket Bolts
Clutch Run-In With 8- Hex Head Socket Bolts
Figure 4-3
Clutch Disassembly & Assembly
Refer to Figure 4-4 on page 25:
If clutch run-in procedure above indicated that one or more
friction disks did not slip, then the clutch must be
disassembled into separate friction disks.
1. Rotate 8 hex head socket bolts (#4) all the way out to
free stop flange (#5).
2. Record position of the lips (up or down) on stop
flange (#5) and then rotate flange and remove it.
3. Remove the following inner components:
a. Spring kit (#6)
b. Pressure flange (#7)
c. 1st Friction Disc (#8)
d. Hub with flange and pull collar (#2 & #3)
e. 2nd Friction disc (#8)
f. Bearing (#9)
IMPORTANT: Check position of lip on stop flange.
(UP or DOWN). Replace stop flange with lip UP if
one spring (#6) is included and DOWN if two springs
(#6) are included.
4. Inspect all components and replace to their original
position. Make certain stop flange (#5) is replaced
with its flanges in its original position. See important
note in Figure 4-4.
5. Fully tighten all 8 hex head socket bolts (#4).
11/01/11
Table of Contents
21270

Shearbolt Protection

Avoid shear bolt breakage by making sure the tiller is out
of the ground before engaging PTO and by engaging
PTO slowly at low engine rpm. Increase engine speed to
540 RPM only after tines are rotating.
IMPORTANT: Replace shear bolts with original
Land Pride equipment from your Land Pride Dealer.
See table below for correct shear bolt and nut part
numbers. Torque shear bolt nuts to 7-9 ft- lbs.
Shear Bolt and Lock Nut Part Numbers
Part No.
RTR10
802-683C
803-278C
RTR15
802-115C
803-011C
Clutch Assembly
Figure 4-4
Part Description
M8 x 45 GR 8.8
M8 Lock Nut (Torque nut to 7-9 ft. lbs.)
5/16"-18 x 2 GR 5 bolt.
5/16"-18 Lock Nut (Torque nut to 7-9 ft. lbs.)
RTR10 & RTR15 Series Rotary Tillers 311-431M
21302
25

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Rtr1550Rtr1558Rtr1042Rtr1050Rtr1058Rtr1566 ... Show all

Table of Contents