INSTALLATION continued

Leg Installation

G24 Series
Your new appliance has been supplied with four 4"(102mm)
adjustable legs. These legs are threaded into holes on the
bottom. Once the legs are installed turn the leveling foot at
the bottom of the leg.
LEG INSTALLATION
UNDERSIDE OF UNIT
Level the appliance by adjustment of leveling bolts or legs.
Use a spirit level and check for level four ways; across front
and back, then down left and right edges. Level any adjacent
units to the fi rst. A griddle may not rest evenly on the
appliance body if it is not properly leveled.

Installation of Banking Plates

G24 Series
All units may be installed independently or banked with
other G24 or E24 Series equipment. To ensure a matching
and permanent fi t between units, a front banking plate is
supplied with each unit. If 2" (51 mm) legs are supplied with
nit, discard leveling bolts and replace with 2" (51 mm) legs.
Part #4519655 Rev.2 (Jan 27/15)
4" [102mm]
ADJUSTABLE LEG
LEVELING FOOT
1. Level each unit by adjusting leveling bolts or legs. Use a
spirit level and level unit four ways; across front and back
and down left and right edges. Level all other units to the
fi rst unit, securing each unit to the adjacent unit.
NOTE: Griddles may not rest evenly on the unit body, if
units are not leveled.
2. Remove upper front panel (if not already removed) by
removing the thumb screws on each side of the panel.
3. Place the banking plate in position, over the two bolts
located in the main sides below the panel mounting
brackets.
NOTE: Install recessed (stepped) centre portion of
banking plate tight to the main sides of the units being
banked. Secure in place with two hex nuts supplied.
4. Replace and secure upper front panels.
5. Connect gas supply line using either rear or bottom inlet,
as desired. A readily accessible approved type of hand
valve should be installed on each supply line. Test For
Leaks.

Installing Equipment on Counter Stands

CS24 Series Stands
1. Assemble and level counter stand as illustrated in the
instructions found in the counter stand carton.
2. Remove and discard leveling bolts on unit to be installed
on the counter stand.
3. Remove only the side, front and rear sheet metal screws
in the main bottom of units to be placed on the outer
sides of the stand.
4. Place units in desired position on the counter stand,
securing the fi rst unit with sheet metal screws removed in
paragraph 3, by inserting the sheet metal screws through
the 9/32 inch (7 mm) diameter holes in stand, into the
holes from which the sheet metal screws were removed.
5. Connect banking plates as described in G24 Series
Installation Of Banking Plates.
6. Secure last unit to the counter stand with sheet metal
screws removed in paragraph 3. Insert sheet metal screws
through the 9/32 inch (7 mm) diameter holes in stand,
into the holes from which the sheet metal screws were
removed.