INSTALLATION OF TRAFFIC LOOPS AND FEEDER CABLES IN SLOTS

Before the work is carried out, the tools listed in the General Principles
Installation handbook (see section 1.3.1) should be available.
2.1

Loop Cable and Slot Dimensions

Loop slots are cut into road surfaces for the installation of the following loop
cables:
998/4/70671/001
998/4/85264/000
998/4/82021/000
The works specification specifies cable to be used.
Slots for the installation of cables must be of sufficient width to permit the free
entry of cables. Minimum slot widths are as listed:
998/4/85264/000
998/4/82021/000
998/4/70761/001
Slot depths are dependent upon the number of turns in the loop or number of
conductors within a slot, as follows:
998/4/85264/000
998/4/82021/000
998/4/70671/001
Note: The number of turns is specified in Section 2.5.
2.2

Positioning of Loops and Loop Tails/Feeders

Loop locations containing the following obstructions should be dealt with as
indicated.

2.2.1 Metal Reinforcing

When installing loops in concrete roads containing a metallic reinforcing
mesh, there must be at least 50 mm of vertical spacing between the top of the
mesh and the bottom of the slot or loop cable. The same rule applies to metal
damp courses found in some elevated roadways.

2.2.2 Buried Metal Objects

Generally speaking, heavy metal objects such as girders and pipes have little
effect on System D and Turning Detector Loops, providing the nearest point is
50 mm or more below the loop.
667/HE/20663/000
50/0.25 EPR insulated
30/0.25 EPR insulated
30/0.25 EPR/PCP insulated
6 mm
8.5 mm
8.5 mm
4 mm x turns/conductors )
6.5 mm x turns/conductors )
6.5 mm x turns/conductors )
Issue 13
L
D
OOP
ETECTOR
Plus 50 mm where
)
slots are cut in a black
top cover, or 25 mm
)
where slots are cut in
concrete.