Standard Procedure - Minelab F3 Operation Manual

Mine detector
Hide thumbs Also See for F3:
Table of Contents

Advertisement

F3 Operations Manual
4.2

Standard Procedure.

preparing it for use as described in Chapter 2 (appropriate
Sensitivity Endcap fitted as directed by the local authority),
complete the THREE step standard procedure as follows:
a. STEP 1
Hold the coil at least 600mm (24ins) from the ground and away
from any metallic objects. Turn the detector on by sliding the
On/Off switch back towards the handle.
Ground
Balance/
Audio Reset
Button
Noise
Cancel
Button
Earset
Socket
Figure 14: F3 Controls
Switch ON
Figure 15: Switching on the Detector
After unpacking the F3 and
On/Off
Switch
P0621-A
P0645-A
22

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents