Figure 11 - Box/Wall Thimble; Figure 12 - Vent Can Height; Mobile Home Installation; Through Roof Framing - Echo DIRECT VENT GAS HEATER Installation And Operating Instructions Manual

Table of Contents

Advertisement

ECHO
FIGURE 11 – BOX/WALL THIMBLE
FIGURE 12 – VENT CAN HEIGHT
X
Consult local codes for minimum vent cap
height above the roof (X).
Pitch (Ratio)
0/12 - 2/12
2/12 - 7/12
7/12 - 12/12
12/12 - 24/12
24/12+
'X'
4"
5 1/2"
6 3/4"
7 1/2"
12 1/2"
Ensure all pipe section are fully twist locked.
Use a suitable round or square support through the
roof. Ensure adequate heat shield protection is
provide. See diagram and chart for minimum
protection (Figure 12).
NOTE: Always check your local codes before
installing venting. Clearances etc, may vary from
state to state (province to province).

Through Roof Framing

Maintain 10" opening relative to the pitch of the
roof.
To prevent water seepage install the flashing with
upper portion slid under the roofing material and the
lower portion over the roofing material.
NOTE: Do not fasten down until the final
adjustments to the vent have been made.

MOBILE HOME INSTALLATION

Direct Vent appliances installed in Mobile Homes
must be secured to the floor in a minimum of two
locations. All four legs have leveling bolts that can
be removed and a lag screw can be used to secure
the heater to the floor and/or hearth pad.
For proper venting, see Figure 6, Figure 14, and
Figure 15.
20