Commissioning - Tyco FlameVision FV300 SERIES User Manual

Infra-red flame detection
Table of Contents

Advertisement

COMMISSIONING

7.
COMMISSIONING
7.1
SYSTEM CHECKS
Before connecting the zone wiring to the control equipment or to the detectors, a general inspection
of the system should be carried out. In particular, the positions of the detectors should be checked
to ensure that the requirements given in the System Design and Installation sections are met.
When the system wiring has been successfully tested and the control equipment commissioned, the
detector electronic assemblies may be fitted. Set the Remote Configuration (Table 3), Delay
Options (Table 4), Alarm Latching (Table 5), Fault Latching (Table 6) and OPM Inhibit (Table
7). The selectins should be recorded in Annex C for future checking during service and
maintenance operations.
7.2
SWITCH AND HEADER SETTINGS
The FV300 FlameVision detectors are very flexible and can be configured for a wide range of
applications. For ease of installation the most common, primary, options are available on DIP
switches located on the back of the detector. Advanced options, such as masking, and entering
location information for the video display are set using the PC configuration tool.
7.2.1
SWITCH LOCATION
7.2.2
CONFIGURATION DIP SWITCHES (SW1)
The primary configuration options can be set on DIP switches located on the back of the detector,
see Fig. 28. The switch settings are described in Table 2. The default, supplied, setting is all
switches off.
SW2
4-20mA MODE
4-20mA
4-20mA
SOURCE
SINK
Fig. 28 Switch Location
43

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents