Remove any protective materials and coatings from all of the parts and the tool. The protective coatings can be
removed by spraying WD-40 on them and wiping it off with a soft cloth. This may need redone several times before
all of the protective coatings are removed completely.
If any parts are missing, do not attempt to plug in the power cord and turn "ON" the machine. The
machine should only be turned "ON" after all the parts have been obtained and installed correctly.

ATTACh SPARK ShIELd ANd gRINdINg ShIELd

Refer to Figure 1.
1. Fit two M5 x 10mm hex screws with an M5 lock
washer and flat washer. Use assembled hex screws
and washers to secure spark shield (A) to the wheel
guard. Spark shield should be approximately 1/8"
from the grinding wheel.
2. Repeat previous step for second spark shield.
3. Use one M5 x 12mm carriage bolt, inserted through
the outermost hole in the spark shield, to attach the
grinding shield (B). Secure using one M5 flat washer
and a threaded thumb knob.
4. Repeat previous step for second grinding shield.

ATTACh TOOL REST

Refer to Figure 2.
1. Attach tool rest support (A) to the inner face of the
wheel guard using two M8 x 10mm hex screws
fitted with M8 flat washers. Finger tighten only.
NOTE: The serrated boss on the tool rest support
should be facing in toward the center of the tool.
2. Attach tool rest (B) to the tool rest support using
one M5 x 18mm thumb screw.
3. Adjust the position of the tool rest support so that
the tool rest is approximately 1/8" from the grinding
wheel (C).
4. Tighten the two M8 x 10mm hex screws on the tool
rest support using the tool wrench provided.
5. Repeat above steps for second tool rest.
UNPACKINg

ASSEMBLY