Maximum horizontal run for a minimum vertical rise
MAXIMUM HORIZONTAL RUN
WITH MINIMUM VERTICAL
o
RISE AND 90 ELBOW
12" SECTION
(DV(LT,TT)36)
24" SECTION
(DV(LT,TT)42)
Minimum vertical rise for maximum horizontal run
Page 16
VENTING FIREPLACE
20"
(508mm)
Figure 24
19'- 5"
(5.9M)
Figure 25
Below Grade Installation
When it is not possible to meet the required vent terminal clearances
of 12" (305mm) above grade level, a snorkel kit is recommended.
It allows installation depth down to 7" (178mm) below grade level.
The 7" (178mm) is measured from the center of the horizontal vent
pipe as it penetrates through the wall.
Ensure the sidewall venting clearances are observed. If venting
system is installed below ground, we recommend a window
well with adequate and proper drainage to be installed around
the termination area.
Typical Basement Installation
3" (76 mm) MINIMUM
48"
(1219 mm)
(457 mm)
MINIMUM
(305 mm)
ABOVE
GRADE
Figure 26
31259-3-0114
18"
12"