1. Steam System
a. Is steam available? ______
b. Have the steam lines been blown out and checked for cleanliness? ______
c. Have the turbine steam inlet and exhaust chambers been checked for foreign material before steam lines are attached? ______
d. Are there adequate pipe hangers and supports on the steam lines and has an analysis of the piping been concluded to eliminate
piping stress on the turbine? ______
e. Have limiting rods been placed on expansion joints when they are used? ______
f. If a trip and throttle valve is supplied, does it have adequate support under it so that no weight or stress is placed
on the turbine? ______
g. Have all steam leak-off lines and drains been piped as indicated on the Dresser-Rand Outline drawing? ______
h. Has an atmospheric relief valve been installed in the exhaust line between the turbine and the first block valve? ______
2. Turbine Preparation
a. Has the turbine been rough aligned to the driven machine and grouted in? ______
b. Have all shipping plugs and/or blind flanges been removed from the oil pipes and lube console and oil lines cleaned
prior to installing? ______
c. Has oil tank been cleaned and inspected in preparation to filling with oil? ______
d. When oil console is supplied by others, has provisions been made to circulate oil and checked for cleanliness without
passing oil through the turbine? ______
e. Is piping complete and water available for oil cooler? ______
f. Has proper oil for turbine and driven machine been obtained and brought to jobsite? ______
g. Has auxiliary oil pump, where supplied, been checked for correct rotation? ______
h. Are pneumatic and electrical connections to the turbine governor and safety devices completed? ______
i. Is piping and wiring to gauge board, where furnished, complete? ______
3. Condensing Turbines Only
a. Has a means been provided to drain the casing while under vacuum? ______
b. Have the condenser condensate pumps been checked for correct rotation? ______
c. Has the condenser hot well level control been checked for correct operation? ______
Signed By: ____________________________________ Date: ____________
Firm Name: ______________________________________________________
Copyright 2009 Carrier Corporation
Manufacturer reserves the right to discontinue, or change at any time, specifications or designs without notice and without incurring obligations.
Catalog No. 04-53170002-01

PRE-START UP CHECK LIST

Printed in U.S.A.
Form 17DA-3SS
Pg CL-1
3-09
Replaces: 17DA-2SS,
17DA-3SO

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Hfc-134a

Table of Contents