INSTALLATION (Continued)
ASSEMBLE OVERHEAD SUPPORT ARM & BAR
Assemble overhead support arm (#25) and (#26) using four
3/8 x 2-1/4" cap screws (#51), four 3/8" nuts (#59), and four
lock washers (#13). Sandwich the warning panel assembly
(#70) between left hand end frame (#2) and the left side
support arm (#25).
Install two overhead clamp castings (#8) onto the overhead
bar (#37) as shown in FIG. 8. Assemble overhead bar
(#37) with two 3/8" x 3/4" cap screws (#48) & two lock
washers (#13) being sure to place overhead clamp castings (#8)
onto overhead bar as shown before assembling. See FIG. 8.
Assemble the overhead clamp assemblies. (#45,46,47,62)
onto the overhead clamp castings (#8). Assemble bumper (# 65)
onto mower clamp weldment (#46). See FIG. 9.
MOUNT GRINDING HEAD ASSEMBLY
Place grinding head assembly onto machine rails. Position
the carriage travel stops (#35) and clamp into place.
Remove grinding wheel guard (#5), install the 6" diameter x 3/8"
wide grinding wheel (#30) and snugly hand tighten. Adjust
the guide finger (#13) and tighten. Then reinstall the grinding
wheel guard (#5).
INSTALL DUST DEFLECTOR SHIELD
Attach the dust deflector shield with two 3/8-16 x 3/4"
cap screws (#40) and two lock washers (#42). Install
Dust Bag (#35) and Hose Clamp (#57). See FIG. 10.
TOOLING BAR COMPONENTS
The reel support centers are mounted horizontally on
the tooling bar. Reposition them vertically on the
tooling bar at this time. See FIGS. 10 and 12.
Assemble the vertical adjusting screw (#33) and lock
(#15). Center the horizontal adjusting screw (#34).
See FIG. 13.
Warning panel assembly must be
installed to protect the operator
and visitors.
The Grinding Head Assembly weighs
approximately 85 lbs (40 kg). To lift,
use power equipment or get adequate
help.
FIG. 12
6
FIG. 8
FIG. 9
FIG. 10
FIG. 13