c) Increase air to reduce CO ² (or increase O ² ) by
about 1%.
d) Re-check the smoke level. It should be zero.
4. Install the sound absorbing burner cover.
5. After about 15 minutes of operation, check the smoke
level and CO ² level. If the CO ² level has increased
significantly, re-adjust the air damper.
F.

CHECK BOILER FUNCTION

1. Start and stop the burner several times to assure
satisfactory operation.
2. Observe boiler operation under normal operation for
a short time. Assure that the boiler temperature is not
increasing too rapidly.
3. Check the system to assure that there are no leaks or
overfilling problems which may cause excessive make
up water to be added. Make up water may cause
liming in the boiler and corrosion in ferrous system
parts.
START-UP PROCEDURE