Operation Verification Tests
Table 2-3 lists the requirements for operation verification, which is a subset of the performance tests.
1
Turn-On Checkout
2
Voltage Programming and Readback Accuracy
3
Current Programming and Readback Accuracy
Note: Record the results of Tests 2 and 3 in the appropriate Performance Test Record sheets
Performance Tests
Performance tests check all the specifications of the power supply. The tests are grouped into constant-voltage mode tests
(Table 2-4) and constant-current mode tests (Table 2-5).
Constant Voltage (CV) Tests
Test Setup
Connect your dc voltmeter leads to only +S and -S (see Figure 2-1), because the power supply regulates the voltage
between these points, not between the + and - output terminals .
Test Procedures
Perform the test procedures in Table 2-4. The CV tests are:
•
Voltage Programming and Readback Accuracy
•
CV Load Effect
•
CV Source Effect
•
CV Noise (PARD)
•
Transient Recovery Time
Note
The tests are independent and may be performed in any order.
14 Verification
Table 2-3. Operation Verification Tests
Test
Refer To
Power Supply Operating Manual
Table 2-4