Commissioning

When the hob has been fully installed it will be necessary to check the
minimum flame setting. To do this, follow the procedure below.
1) Turn the gas tap to the MAX position and ignite.
2) Set the gas tap to the MIN flame position then turn the control
knob from MIN to MAX several times. If the flame is unstable or is
extinguished follow the procedure below.
Procedure:
1) Re-ignite the burner and set
to MIN.
2) Remove the control knob.
3) You can find two different
adjustment screw locations
according to the gas tap (see
diagram). The "b" type has
the adjustment screw
located down the centre of
th egas tap control shaft. The
"c" type has the by pass
screw located to the side of
the gas tap itself.
To adjust, use a thin bladed screwdriver and turn the adjustment
screw until the flame is steady and does not extinguish, when the
knob is turned from MIN to MAX. Repeat this procedure for all
burners.

Pressure Testing

1) Remove left hand pan support and front left burner cap and crown.
2) Fit manometer tube over the injector.
3) Turn on the burner gas supply and ignite another burner supply.
The pressure reading should be nominally 20mbar and must be
between 17 mbar and 25mbar.
4) Turn off the burner supplies.
FO 1032
a) Minimum adjustment screw
b) Tap