Contractor's proposal price shall include the cost of replacing existing wiring, conduit,
2.
and raceways as required.
1.09 SEQUENCING
A.
Description
This implementation plan describes the general approach that shall be followed in order to
minimize the time for the access control systems to be operational.
B.
Approach
Contractor shall plan and schedule all work in such a sequence as to minimize the time before
the system is operational. The following is a suggested work sequence:
1.
Order all equipment needed and notify any subcontractors to schedule their participation.
2.
Perform all system layout work.
3.
Insure there are an adequate number of power receptacles available to operate all security
equipment and coordinate with OWNER as to where power is available.
4.
Provide shop drawings to verify location of all equipment, conduit runs, power
connections, etc. Submit shop drawings to OWNER Project Manager.
5.
Coordinate with OWNER to provide space for the placement of all monitoring, control
and recording equipment.
6.
Prepare and pre-test all equipment to the greatest extent possible.
7.
Install all equipment.
8.
Test and inspect all systems.
9.
Perform all other Work as required.
10.
Provide as-built drawings.
11.
Perform the Acceptance Test.
12.
Provide training.
1.10 SCHEDULING
The Contractor, within five (5) days after being awarded the contract, shall prepare and submit for
OWNER's information, an estimated progress schedule for the Work. The progress schedule shall be
related to the entire project, and shall indicate start and completion dates.

1.11 WARRANTY

A.
Contractor warrants that all Work furnished (material and labor) under this Contract will be of
good quality, free from faults and defects, and in conformance with the Project Drawings and
Specifications.
B.
Contractor shall provide parts and labor guarantee on all Work. Unless otherwise specified
herein, Contractor's guarantee shall be for a period of one (1) year from date of Acceptance,
except where any specific guarantees from a supplier or equipment manufacturer extends for a
longer time.
Contractor's guarantee shall cover all costs associated with troubleshooting, repair, and
C.
replacement of defective Work, including costs of labor, transportation, lodging, materials, and
equipment.
D.
Guarantee shall not cover any damage to material or equipment caused by accident, misuse,
unauthorized modification or repair by OWNER, or acts of god.
OWNER / November 22, 2013
Canon model VB-S800D A&E Specifications
28 23 00 - 8
Video Surveillance System

Advertisement

Table of Contents
loading

Table of Contents