Testing the New Battery Module

After installing the new battery module, press the Test/Alarm Reset button. Refer to the
section, "Initiating a Self-Test," in Chapter 2 for more information on initiating a self-test.
IMPORTANT: The UPS schedules the battery test, but will not execute the test until the batteries are at
least 90 percent charged.
If the installation has been successful, the Alarm LED will not be illuminated.
If the installation has not been successful, the Alarm LED turns red and the LCD menu
indicates an alarm. If this occurs, repeat the procedures in the "Replacing the Batteries"
section of this chapter, and check the battery terminal connections. If the Alarm LED is still
red, refer to Chapter 5, "Troubleshooting," for more information on the cause of the alarm.
IMPORTANT: The batteries will charge to 80 percent of their capacity within approximately
three hours. Charge the batteries for 24 hours before using the UPS to supply backup power to devices.
The load may not be fully protected for 48 hours.
Conducting a Battery Commissioning Test
When replacing battery modules, it is recommended running a battery commissioning test.
This test will set a base line so that the UPS accurately displays battery run-time. Refer to the
section, "Setting the Hardware Configuration," in Chapter 3 for instructions on enabling the
battery commissioning test.
NOTE: The battery commissioning test runs in the background. Once enabled, the test can take up to
three days to run.

Disposing of Used Batteries

The spare battery kit includes the instructions and packaging required to return used batteries
to the appropriate location for disposal.
HP Uninterruptible Power System R12000 XR Models User Guide
Batteries, battery modules, and accumulators should not be disposed of
together with the general household waste. In order to forward them to
recycling or proper disposal, use the public collection system or return them
to HP, your authorized HP Partners, or their agents.
Battery Maintenance
4-5