Rigging and Handling

Confirm that factory installed (if any)
attachment brackets are in place and
screws tight, before rigging. The unit
will ship either assembled or as
sections. Before preparing the unit for
lifting, estimate the approximate center
of gravity for lifting safety. Because of
placement of internal components, the
unit
weight
may
be
distributed, with more weight in the coil
and fan area. Approximate unit weights
are given in Appendix A & B.
Always apply good rigging procedures
when lifting a unit. Before hoisting the
unit into position, be sure that a proper
method of rigging is used, with straps
or slings and spreader bars for
protection and safety during lifting.
Always test-lift the unit to determine
exact unit balance and stability before
hoisting it to the installation location.
WARNING
!
NEVER ASSEMBLE OR BOLT
SECTIONS OR SUBASSEMBLIES
TOGETHER BEFORE RIGGING.
ALWAYS
RIG
SECTIONS
SUBASSEMBLIES AS RECEIVED
FROM THE FACTORY.
WARNING
!
DO NOT LIFT THE UNIT WITHOUT
TEST-LIFT FOR BALANCE AND
RIGGING. DO NOT LIFT THE UNIT
ABOVE PERSONNEL. FAILURE TO
OBSERVE THESE WARNINGS MAY
RESULT IN PERSONAL INJURY,
DEATH OR EQUIPMENT DAMAGE.
(See Appendix A & B for components
weight).
Rigging and Handling

Off Loading

A specific lifting method for offloading
the units is recommended as follows
(See Figure 2):
1. 75mm-diameter lifting holes,or
certified lifting lugs, are provided on
the unit base frame.
2. ALL LIFTING POINTS in one axis of
the unit must be used when
unevenly
offloading and moving the unit.
3. Slings and speader bars are to be
provided by the rigger and attached
to ALL LIFTING POINTS.
4. The minimum rated lifting capacity
(vertical) of each sling and spreader
bar should be no less than the
shipping weight.
5. The unit must be lifted with care,
avoiding shock load by lifting the unit
slowly and evenly.
!
ENSURE SLINGS DO NOT FOUL ON
UNIT PROTRUSIONS.
THE CENTRE OF GRAVITY WILL
VARY PER UNIT... POSITION THE
SLING AND SPREADER BARS
OR
CAREFULLY TO COMPENSATE FOR
THIS.

Moving To Position On Site

TRANE Quantum
supplied in sections modules, flat
packed, or as a complete unit, in
accordance with the relevant assembly
drawings. Any necessary use of force
during unloading or movement of the
units must only be applied via the unit
base frame or shipping pallet.
WARNING
TM
Air Handler are
5
TRANE
WARNING
!
NEVER LIFT THE UNITS BY COIL
CONNECTIONS OR BY ANY OTHER
PROTRUSIONS.
THE ROOF IS NOT DESIGNED TO BE
WALKED ON, BUT IF THIS IS
UNAVOIDABLE, ENSURE A MORE
EVEN WEIGHT DISTRIBUTION BY
THE USE OF BOARDS.
FAILURE TO DO SO MAY RESULT IN
SEVERE PERSONAL INJURY OR
DEATH.
Figure 2