System
Pre-Start Procedure

Installation Checklist

Complete this checklist once the unit
is installed to verify that all recom-
mended procedures have been
accomplished before starting the sys-
tem. Do not operate the system until
all items covered by this checklist are
complete.
[ ] Inspect unit location for proper
required service clearances.
[ ] Inspect unit location for proper free
air clearances.
[ ] Inspect unit location for secure,
level mounting position.
Refrigerant Piping
[ ] Performed initial leak test?
[ ] Connected properly sized and con-
structed liquid and discharge lines
to the connection stubs at both the
indoor and outdoor units?
[ ] Insulated the entire discharge line?
[ ] Insulated portions of liquid line
exposed to extremes in tempera-
ture?
[ ] Evacuated each refrigerant circuit
to 350 microns?
[ ] Charged each circuit with proper
amount of R-410a?
Electrical Wiring
[ ] Provided unit power wiring (with
disconnect) to proper terminals in
the unit control section?
[ ] Installed system indoor thermo-
stat?
[ ] Installed system low voltage inter-
connecting wiring to proper termi-
nals of outdoor unit, indoor unit
and system thermostat?