Table of Contents SAFETY RULES Safety Rules ..........Inside Front Cover General Information ..............2 SAVE THESE INSTRUCTIONS! Read the fol- 1.1 Introduction ................2 lowing information carefully before attempting 1.2 Unpacking .................. 2 to install, operate or service this equipment. 1.3 Equipment Description ..............
Safety Rules These safety warnings cannot eliminate the hazards that they • Competent, qualified personnel should install, operate and ser- indicate. Common sense and strict compliance with the special vice this equipment. Adhere strictly to local, state and national instructions while performing the service are essential to prevent- electrical and building codes.
General Information INTRODUCTION • Any loads, including central air conditioners, can be controlled via a contactor that must be purchased separately. Up to four This manual has been prepared especially for the purpose of famil- contactors can be controlled by the load shed module. The LSM iarizing personnel with the design, application, installation, opera- supplies the 120 Vac to energize each contactor coil.
Installation TRANSFER SWITCH CONNECTING POWER SOURCE ENCLOSURE AND LOAD LINES The standard switch enclosure is a National Electrical Manufacturer’s Association (NEMA) and UL 3R type. UL and NEMA 3R type enclo- sures primarily provide a degree of protection against falling rain ...
Installation CONNECTING LOAD SHED Before connecting wiring cables to terminals, remove any surface oxides from the cable ends with a wire brush. All power cables MODULE (LSM) CONNECTIONS should enter the switch next to transfer mechanism terminals. The LSM can control an air conditioner (24 Vac) directly or a sepa- If ALUMINUM conductors are used, apply corrosion inhibitor to rate contactor (120 Vac) which can control any load connected to conductors.
Operation FUNCTIONAL TESTS AND 3.2.1 CLOSE TO NORMAL SOURCE SIDE ADJUSTMENTS Before proceeding, verify the position of the switch by observing window “A” in Figure 3.1 on page 6. If window “A” reads “ON”, Following transfer switch installation and intercon- the contacts are closed in the normal position, no further action is nection, inspect the entire installation carefully.
Measure across ATS terminal lugs E1 to E2; E1 to NEUTRAL and E2 to NEUTRAL. a. Frequency .......... 60-62 Hz b. Terminals E1 to E2 ......240-246 VAC c. Terminals E1 to NEUTRAL ....120-123 VAC d. Terminals E2 to NEUTRAL ....120-123 VAC Generac ® Power Systems, Inc.
Operation GENERATOR TESTS UNDER TESTING LOAD SHED MODULE LOAD (LSM) Set the generator's main circuit breaker to its OFF or OPEN A Test pushbutton is provided on the bottom of the LSM to test the position. operation of the tested functions. The Test button will work when the ATS is in the Utility or the Generator position.