Ericsson EDN312 Installation Manual
Ericsson EDN312 Installation Manual

Ericsson EDN312 Installation Manual

Ethernet dsl access ip dslam

Advertisement

EDN312 Installation Guide
Ethernet DSL Access
IP DSLAM

Advertisement

Table of Contents
loading

Summary of Contents for Ericsson EDN312

  • Page 1 EDN312 Installation Guide Ethernet DSL Access IP DSLAM...
  • Page 2 The contents of this document are subject to revision without notice due to continued progress in methodology, design and manufacturing. Ericsson shall have no liability for any error or damage of any kind resulting from the use of this document.
  • Page 3: Table Of Contents

    Contents 3.1.1 3.1.2 Reference List 1/1531-HSD 101 41 Uen A 2004-01-30 Introduction Revision History Environmental and Space Requirements Cabling Cabling of Subscriber Lines Cabling Lines Wiring EDGE Connectors Cabling of Ethernet Connections Mounting the IP DSLAM Verifying the Installation Verification without Connection to PEM Verification with the Local Craft Tool Verification Using PEM...
  • Page 5: Introduction

    Revision History The guide is valid for EDA 1.3. Please refer to the Release Notes for valid versions of the EDN312 IP DSLAM and the application SW. Other product versions with functions not described in this guide may be available.
  • Page 6: Environmental And Space Requirements

    Outdoor Cabinet Installation Guide. Mounting in the rack must be done in such a way that there is sufficient space to allow airflow around the EDN312 as shown in Figure 1 on page 3. Caution!
  • Page 7 Environmental and Space Requirements The distance between the IP DSLAMs must be at least 20 mm so that an IP DSLAM can be dismounted without interfering with the adjacent IP DSLAMs. Figure 1 Space Requirements when Mounting in Rack or Cabinet 1/1531-HSD 101 41 Uen A 2004-01-30...
  • Page 8: Cabling

    Cabling Cabling Cabling of Subscriber Lines Before the IP DSLAM is mounted the connections between the Line MDF and the Exchange MDF have to be rewired. The wires are disconnected, and then reconnected through typically a Broadband MDF and the EDA System according to planning.
  • Page 9: Wiring Edge Connectors

    3.1.2 Wiring EDGE Connectors It is recommended to follow the “Best practice” wiring procedure when wiring the EDGE connectors. The EDGE connector can be mounted by using a Tool Kit. The kit consists of a wiring bracket-tool and an LSA+ inserter-tool. Figure 3 on page 5 shows how to mount the wiring bracket-tool on the rods in a subrack.
  • Page 10 Cabling Figure 4 Strip approximately 20 cm off the new cable and tie it up with a cable tie to the existing cable as illustrated in Figure 5 on page 7. Alternatively, make a loop around the cable guide. Note: It is recommended to use 0.4 mm thick wiring cables Mounting the EDGE Connectors 1/1531-HSD 101 41 Uen A 2004-01-30...
  • Page 11 Figure 5 Connect and cut the wires (one action using the KRONE LSA+ Insertion- Tool S, see Figure 6 on page 7) by placing the Insertion tool above the slit (place the cutting end towards the connector’s center), and firmly press towards the connector.
  • Page 12: Cabling Of Ethernet Connections

    Cabling Figure 7 Cabling of Ethernet Connections The EDN312 IP DSLAM is connected to the network with cat. 5 straight through standard LAN cables. The total cable length from a switch to the IP DSLAM must not exceed 100 m and must conform to category 5 standard for LAN cables.
  • Page 13: Mounting The Ip Dslam

    Mounting the IP DSLAM The illustration below shows how to mount the EDN312 after the subscriber lines, exchange lines through the EDGE connector have been pulled. The EDGE connector is removed from the bracket-tool and inserted in the rear of the IP DSLAM. The IP DSLAM has been labelled with “line” on one side and “exchange”...
  • Page 14: Verifying The Installation

    Verifying the Installation Verifying the Installation The purpose of the verification is to ensure the following: No errors in the rewiring of the subscriber lines The old services (POTS or ISDN) function The physical installation of the EDA Access Domain nodes was done correctly The power and Ethernet connections function It is possible to make an ADSL connection to a CPE modem...
  • Page 15: Verification With The Local Craft Tool

    POTS or ISDN line The ECN320 Local Craft Tool When the EDN312 IP DSLAM is embedded in an EAN as for example the EDN288 and connected to the ECN320 Ethernet Controller Node the line verification is done by means of the ECN320 Local Craft Tool. The ECN320 Local Craft Tool is an application used for checking the function of each IP DSLAM embedded in an EAN.
  • Page 16: Verification Using Pem

    Verifying the Installation 2. Copy 24 configuration files with line configurations from the LCT tool to the ECN320 flash disk. 3. Restart the embedded IP DSLAMs by using the Command Line Interface (CLI) 4. Test the ADSL lines by connecting a CPE modem to each line one at a time.
  • Page 17 This method is similar to activating real subscribers. In order to use this method the following preconditions have to be fulfilled: The PEM installation has succeeded The PEM configuration of the network has been done The servers in the network are running All registration has been transferred to the PEM The Service Configuration Manager is used for this task.
  • Page 18: Reference List

    Reference List Reference List System Overview, 1/1551-HSC 901 26/4, Ericsson AB 2004 PEM User’s Guide, 1553-AOM 901 018/3, Ericsson AB 2004 EDN312 User’s Guide,1/1553-HSD 101 41, Ericsson AB 2004 Subrack Installation Guide, 1/1531-HSC 901 026/4, Ericsson AB 2004 Outdoor Cabinet Installation Guide, 1531-1/BFM 901 097, Ericsson AB...
  • Page 20 Ericsson AB Ericsson AB - 2004 All Rights Reserved www.ericsson.com 1/1531-HSD 101 41 Uen A 2004-01-30...