Develop the Schedule
The following schedule lists the sequence of events for an ideal system installation.
60 days before installation
— Floor plan design completed and mailed to Hewlett-Packard
30 days before installation
— Primary power and air conditioning installation completed
— Telephone and data cables installed
— Fire protection equipment installed
— Major facility changes completed
— Special delivery requirements defined
— Site inspection survey completed
— Delivery survey completed
— Signed copy of the site inspection and delivery survey mailed to Hewlett-Packard
— Site inspection and predelivery coordination meeting arranged with a Hewlett-Packard Site
Preparation Specialist to review the inspection checklist and arrange a solution delivery schedule.
Solution delivery date
— Final check made with an Hewlett-Packard Site Preparation Specialist to resolve any last minute
problems