Condensate Trap Filling; Gas System Start-Up; Boiler Start Up (Ignition) - Immergas VICTRIX PRO 80 2ErP Instruction Booklet And Warning

Hide thumbs Also See for VICTRIX PRO 80 2ErP:
Table of Contents

Advertisement

1.22 CONDENSATE TRAP FILLING.

On first lighting of the boiler combustion products may come out
the condensate drain; after a few minutes' operation check that this
no longer occurs. This means that the trap is filled with condensate
to the correct level preventing the passage of combustion products.

1.23 GAS SYSTEM START-UP.

To start up the system, refer to the technical standard in force: This
divides the systems and therefore the start-up operations into three
categories: new systems, modified systems, re-activated systems.
In particular, for new gas systems:
- open windows and doors;
- avoid presence of sparks or open flames;
- bleed all air from the pipelines;
- check the seal of the internal system by following the instructions
provided by the technical regulations in force (refer to the per-
taining local regulations for the "sealing test" on systems served
by single or cascade generators with a nominal thermal capacity
greater than 35 kW.
22

1.24 BOILER START UP (IGNITION).

In order to issue the Declaration of Conformity required by the
regulations in force, one must fulfil the following requirements to
commission the boiler (the operations listed below must only be
performed by qualified personnel and in the presence of staff only):
- check that the internal system is properly sealed according to the
specifications set forth by regulations in force. Up to operating
pressures of 40 mbar it is also possible to use the testing method
adopted by the technical regulations in force for systems served
by single appliances (or in cascade set-up), with nominal thermal
capacities greater than 35 kW. For greater pressure levels you will
need to refer to legislation in force and/or other effectively tried
and tested methods;
- make sure that the type of gas used corresponds to boiler settings;
- check that there are external factors that may cause the formation
of fuel pockets;
- switch the boiler on and check correct ignition;
- make sure the fan rpm matches the value provided in the book
(Par. 4.1);
- ensure that the safety device intervenes in the event of gas supply
failure and check the relative intervention time;
- check activation of the main switch located upstream from the
boiler and in the boiler;
- check that the intake and/or exhaust terminals (if fitted) are not
blocked.
The boiler must not be started up even if only one of the checks
should be negative.
The Immergas Authorised After-sales Centre can
carry out the initial boiler check (point 2.3) required
to activate the warranty of Immergas solely upon
completion of commissioning by an installer. The test
certificate and warranty is issued to the user

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the VICTRIX PRO 80 2ErP and is the answer not in the manual?

Questions and answers

This manual is also suitable for:

Victrix pro 100 2erpVictrix pro 120 2erp

Table of Contents