QUICK INSTALLATION GUIDE
GWU-GreenE SYSTEM
Copyright Declaration
The copyright of this manual belongs to Greenworks North America, LLC. Any corporation
or individual should not plagiarize, partially or fully copy (including software, etc.), and no
reproduction or distribution of it in any form or by any means. All rights reserved.
Greenworks North America, LLC reserves the right of final interpretation.
320102087402
UL
www.greenworkstools.com

Advertisement

loading

Summary of Contents for GreenWorks PowerHub GWU-GreenE SYSTEM

  • Page 1 Copyright Declaration Greenworks North America, LLC The copyright of this manual belongs to Greenworks North America, LLC. Any corporation or individual should not plagiarize, partially or fully copy (including software, etc.), and no Add: 500 South Main Street, Suite 450 Mooresville, NC 28115 reproduction or distribution of it in any form or by any means.
  • Page 2: Packing List

    Packing list 1. Packing List • Packing list of inverter Item Name Description Inverter X1 Product Mental cover X1 Protect the inverter Bracket X1 Support the inverter Fix the bracket Self-tapping screwX12 Expansion boltX12 Fix the bracket WasherX12 Fix the bracket M5X10 screwX10 Fix the cover, cable protective guard and cover fixing plate Grounding terminalX5...
  • Page 3 Packing List Packing list Accessories for Both Floor and Wall Mounting (Separate Accessory Box) • Packing list of battery BMS (TBMS-MCS60060) Item Name and Quantity Description Product User ManualX1 Guide the installation and maintenance One Battery Module (TP-HS50×1): Item Name and Quantity Description Base supportX2 Support the base...
  • Page 4: Overview Of Terminals

    Packing List Overview of Terminals • Packing list of BI 2. Overview of Terminals • Terminals and breaker of inverter Inverter power terminal (Purchased by customer) Strip Length Terminals Type Cross-sectional Area Range PV terminals 10-8 AWG 0.47 in / 12 mm 90°C(194°F), 600 V, copper 12-8 AWG (3.8KW), AC terminals...
  • Page 5: Right Side View

    Overview of Terminals Overview of Terminals Inverter communication terminal (Purchased by customer) • Terminals breaker of battery Torque Terminals Port Pin Type Range Strip Length (in-lbs) Pin 1: SYSR_L COMM Pin 2: SYSR_H terminal Pin 3: CAN_L CAT5 or 24-18 AWG better Pin 4: CAN_H COMM in...
  • Page 6 Overview of Terminals Overview of Terminals BI communication terminal (Purchased by customer) • Terminals breaker of BI Torque Terminals Port Pin Type Range Strip Length (in-lbs) Pin 1: RESERVE 20 21 22 Pin 2: RESERVE Pin 3: CAN_L CAT5 or 24-18 AWG better 16 17 18...
  • Page 7 Overview of Terminals Mechanical Installation Torque 3. Mechanical Installation (Floor-mounting) Terminals Port Pin Type Range Strip Length (in-lbs) Pin 1: CT L1B+ • Weight and mounting height instructions Shielded, CT L1B terminal twisted pair Pin 2: CT L1B- Pin 1: CT L2A+ Shielded, CT L2A terminal twisted pair...
  • Page 8 Mechanical Installation Mechanical Installation Step 2 Mount the battery module • Mount the battery Step 1 Mount the base Hand remove Hand remove Bottom view M8*85 × 4 Top view Marker Measuring tape Mark 8.8 lbf.in / 1.0 N·m...
  • Page 9 Mechanical Installation Mechanical Installation Ø 0.39 in./10 mm for Wall Bracket 90° ≥3.54 in /90 mm CAUTION! Please re-mount the dust cover to the battery module before drilling holes to avoid dust falling into the interface and do remember to remove the dust cover again after the installation wall bracket completed.
  • Page 10 Mechanical Installation Mechanical Installation Mark Attach screw but not tighten, and align the hole location of Platen (3 holes) × 2 battery M5*10 Screw × 6 2.2-2.5 N·m Tapping Screw × 2 Washer × 2 Wall Bracket × 2 Mark Let the Platen Let the Platen down...
  • Page 11 Mechanical Installation Mechanical Installation Step 3 Mount the BMS • Mount the inverter Screw in the two M4 screws, adjust the bracket to be firmly attached on the wall surface and tignen M4 screws Hand remove 4.4 lbf.in / 0.5 N·m Round holes 8.8 lbf.in / 1.0 N·m...
  • Page 12 Mechanical Installation Mechanical Installation Φ4 drill for wooden wall Φ10 drill for concrete wall Depth: 2.16 in / 55 mm 26.5 lbf.in / 3.0 N·m CAUTION! Remove the screws on the bracket and disassemble the bracket before drill holes. Back view Front view For wooden wall, For solid concrete wall,...
  • Page 13 Mechanical Installation Mechanical Installation Inverter Dowel pins Pins holes 8.8 lbf.in / 1.0 N·m Left side view Right side view 8.8 lbf.in / 1.0 N·m 8.8 lbf.in / 1.0 N·m...
  • Page 14 Mechanical Installation Mechanical Installation • Mount the BI 16 in/406 mm This step is not required in case of wooden wall. Φ4 drill for wooden wall Φ10 drill for concrete wall Depth: 26.5 lbf.in / 2.16 in / 55 mm 3.0 N·m...
  • Page 15 Mechanical Installation Mechanical Installation • Drill a hole in the back (Not recommended) Corresponds to the holes below the perforated paper Hang the BI on the bracket Drill the hole with a hole cutter. Choose 1 inch or 2inch size (Metal chips must be cleaned after drilling) Secure the BI 26.5 lbf.in /...
  • Page 16 Mechanical Installation Mechanical Installation 4. Mechanical Installation (Wall-mounting) Lock nut, waterproof gasket(outside), conduit NOTE! Prohibit the flow of water inside the tubing water into the machine! 17.7 lbf.in / 2.0 N·m The top of the nut and contact surface of the threads must be cleaned after locking Cylindrical plastic the nut, as well as the contact surface between...
  • Page 17 Wiring Connection on the Inverter Mechanical Installation 5. Wiring Connection on the Inverter • AC cable 12–8 AWG (for GWU-HYB 3.8 DH) Cylindrical plastic 10–8 AWG (for GWU-HYB 5.0 DH / bubble spirit level 6.0 DH / 7.6 TH) 26.5 lbf.in / 3.0 N·m 0.47 in / 12 mm For solid wood wall For concrete wall...
  • Page 18 Wiring Connection on the Inverter Wiring Connection on the Inverter for PV • GND cable • Communication cable connection Inverter Inverter for AC connection 120-Ohm terminating resistor 3 2 1 3 2 1 MLPE MLPE Inverter Inverter 8 AWG 0.47 in / 12 mm COMM IN COMM OUT COMM IN...
  • Page 19 Wiring Connection on the Inverter Wiring Connection on the Inverter Diagram for communication connection steps between inverters Diagram for communication connection steps between inverter and BI Step 1 Step 2 Step 1 Step 2 Strip Length Strip Length 0.24 in / 6 mm 0.24in./6mm 24-18 AWG Conduit...
  • Page 20 Wiring Connection between Inverter and Battery Wiring Connection between Inverter and Battery 6. Wiring Connection Between Inverter and Battery • BAT+, BAT- and COMM cable Inverter BAT+, BAT- and COMM cable originally connected on side of inverter. BAT+ Battery COMM BAT- Connection between inverter and battery On the side of inverter...
  • Page 21 Wiring Connection on the BI Wiring Connection on the BI 7. Wiring Connection on the BI 7.1 Connect Inverter Conductors to BI Neutral-Ground Bonding Strap-factory installed • • AC cable Remove Neutral-Ground bonding strap from BI if not installed as service equipment.
  • Page 22 Wiring Connection on the BI Wiring Connection on the BI 7.2 Connect Generator and EPO Conductors to BI • AC cable of generator • Communication cable of generator and EPO Step 1 Step 2 Strip Length 0.24 in / 6 mm 24-16 AWG Generator Conduit...
  • Page 23 Wiring Connection on the BI Wiring Connection on the BI 7.3 Connect Load Conductors to BI 7.4 Connect Grid Conductors to BI • AC cable Before installing a main breaker 6-4 AWG 1.77 in / 45 mm 4/0 AWG 1.25 in / 32 mm 6-4 AWG 1.77 in / 45 mm 4/0 AWG 1.25 in / 32 mm Wirings...
  • Page 24 Wiring Connection on the BI 7.5 Connect CT to BI A set of CTs (CT L1A , CT L2A,200A) has been built in the BI. In some application scenarios ,it can measure both load and generation and there is no need to connect external CTs.But in some application scenarios,such as Partial-Home Backup solution,connecting external CTs (CT L1B , CT L2B) to measure total current both load and generation is needed.