1. Cylinder head air bleed bolt
19. When coolant begins to flow out of the bolt
hole, tighten the cylinder head air bleed bolt to
the specified torque.
Tightening torque:
Cylinder head air bleed bolt:
10 Nm (1.0 m·kgf, 7.2 ft·lbf)
20. Start the engine and let it idle for ten minutes.
21. Rev the engine five times.
22. Pour the recommended coolant into the radia-
tor until it is full.
23. Stop the engine and allow it to cool. If the cool-
ant level has dropped after the engine has
cooled, add sufficient coolant until it reaches
the top of the radiator, and then install the ra-
diator cap.
24. Start the engine, and then check for coolant
leakage.
TIP
If any leakage is found, have a Yamaha dealer
check the cooling system.
25. Install the V-belt cooling duct, and then tighten
the clamp screw.
26. Install the footboard by installing the bolts and
nuts, and then tighten them to the specified
torques.
8-37
8