Resistance Measurement Of Transmission Cable (Measure With Breaker Off); Pipe Installation Ii; Sealing Test; Vacuum Process - Fujitsu AIRSTAGE AJY072LNTCH Installation Manual

Outdoor unit
Table of Contents

Advertisement

7. 7.
Resistance measurement of transmission cable
(Measure with breaker OFF)
Do not turn on the power if the resistance between the terminals of the transmis-
sion cable is abnormal. Otherwise, the circuit board may be damaged.
Measure the resistance between 2 terminals of a transmission cable.
(1) Transmission cable connecting indoor units, outdoor units, and signal
amplifi ers
Measure the resistance of the signal amplifi er terminal and the terminal of the
indoor and outdoor units connected farthest away from the device where terminal
resistor is measured.
A value from the table is displayed, depending on the distance from the signal
amplifi er and the device where the terminal resistor is set.
This value is an estimate.
(2) Transmission cable connecting outdoor units in a refrigerant system
The resistance between the terminals of the transmission cable is 45-60Ω.
This value is an estimate.
Distance from termination resistor (m)
0 ~100
~ 200
A short circuit somewhere or 2 or more termination
0 ~ 50
resistors are connected
50
60
70
80
90
100
110
120
130
140
150
160
170
180
190 ~
Faulty contact or wiring length over 500 m
1K ~∞
Faulty contact, open circuit, or no termination resistor

8. PIPE INSTALLATION II

Fig. A Connection system
A) In case of connecting 1 outdoor unit
Outdoor unit
Indoor
Indoor
unit
unit
B) In case of connecting multiple outdoor units
Outdoor unit
Outdoor unit
Indoor
unit
En-21
CAUTION
~ 300
~400
~500
Pressure regulating
valve
Pressure gauge
Nitrogen
Vacuum
Scale
pump
Pressure regulating valve
Pressure gauge
Indoor
Vacuum
unit
Scale
pump
Fig. B
Valve
Open
Close
Cap
Table. A
Valve type
Liquid
Gas
8. 1.

Sealing test

• Use only nitrogen gas.
Never use refrigerant gas, oxygen, in fl ammable gas or poisonous gas to pressur-
ize the system. (If oxygen is used. There is danger of an explosion.)
• Do not shock during sealing test.
It can rupture the pipes and cause serious injury.
• Do not turn on the power unless all operations are complete.
• Do not block the walls and the ceiling until the sealing test and charging of the
refrigerant gas have been completed.
After connecting the pipes, perform a sealing test.
Recheck that the spindle of the 3-way valve are closed before performing a sealing
test. (Fig. B)
Pour nitrogen gas through both the liquid pipe and the gas pipe.
Pressurize nitrogen gas to 4.2 MPa to perform the sealing test.
Check all fl are connection areas and brazed areas.
Then, check that the pressure has not decreased.
Compare the pressures after pressurizing and letting it stand for 24 hours, and check
that the pressure did not decreased.
* When the outdoor temperature changes 5 °C, the test pressure changes 0.05
MPa.
If the pressure has dropped, the pipe joints may be leaking.
If a leakage is found, immediately repair it and perform a sealing test again.
* Decrease the pressure of nitrogen gas before brazing
After completing the sealing test, release the nitrogen gas from both valves.
Release the nitrogen gas slowly.
8. 2.

Vacuum process

Do not turn on the power unless all operations are complete.
If the system is not evacuated properly, its performance will drop.
• If moisture enter the piping, follow below. (i.e., if doing work during the rainy
season, if the actual work takes long enough that condensation may form on the
inside of the pipes, if rain might enter the pipes during work, etc.)
• After operating the vacuum pump for 2 hours, pressurize to 0.05 MPa (i.e.,
vacuum breakdown) with nitrogen gas, then depressurize down to -100.7kPa
(-755mmHg) for an hour using the vacuum pump (vacuum process).
Nitrogen
• If the pressure does not reach -100.7kPa (-755mmHg) even after depressurizing
for at least 2 hours, repeat the vacuum breakdown - vacuum process.
After vacuum process, maintain the vacuum for an hour and make sure the pres-
sure does not rise by monitoring with a vacuum gauge.
Evacuation procedure
1) Remove the caps of the gas pipe and liquid pipe and check that the valves are
closed.
2) Remove the charging cap.
3) Connect a vacuum pump and a pressure gauge to a charging hose and connect
it to the charging port.
4) Activate the vacuum pump and vacuum the indoor unit and connection piping
until the pressure gauge becomes -100.7kPa (-755mmHg).
Evacuate from both the gas pipe and the liquid pipe.
5) Continue evacuating the system for 1 hour after the pressure gauge reads
-100.7kPa (-755mmHg).
6) Remove the charging hose and reinstall the charging cap.
Charging cap
Spindle
Open
Close
Spindle
Cap
9.0 to 12.0 N·m
20.0 to 24.0 N·m
(90 to 120 kgf·cm)
(200 to 240 kgf·cm)
27.0 to 33.0 N·m
25.0 to 30.0 N·m
(270 to 330 kgf·cm)
(250 to 300 kgf·cm)
CAUTION
CAUTION
Hexagon
wrench
Charging cap
12.5 to 16.0 N·m
(125 to 160 kgf·cm)
12.5 to 16.0 N·m
(125 to 160 kgf·cm)

Advertisement

Table of Contents
loading

Table of Contents