Step 1: Activating the System
6. Close the inverter cover b y tightening the screws with a torque of 3.0 N*m/ 2.2 lb*ft.
7. If an additional external DC switch is installed between the power optimizers and the inverter(s) then
turn it ON.
A status screen similar to the following appears on the LCD panel:
V a c [ V ]
2 4 0 . 7
P _ O K :
- - - - - - - - - - - - - - -
8. Verify that the following information appears on the LCD panel:
P_OK: Appears only upon pairing process completion and first telemetry reception from the
l
power optimizers. Indicates connection to the power optimizers and that at least one power
optimizer is sending monitoring data.
000/000: Appears only upon first telemetry reception from the power optimizers. Indicates the
l
number of power optimizers that have been paired to this inverter.
S_OK: the connection to the SolarEdge monitoring platform is successful (should appear only if
l
the inverter is connected to the server). If S_OK is not displayed and the inverter is connected to
the server, refer to Errors and Troubleshooting on page 54.
Vac [V]: the grid AC output voltage. Verify the correct value.
l
Vdc [V]: The DC input voltage of the longest string connected to the inverter. T here should be a
l
safety voltage of 1V for each power optimizer in the string.
NOTE
A measurement error on the inverter LCD of ±3 V is acceptable.
Pac [w]: the AC output power (should be 0.0 since the inverter is OFF).
l
OFF: The inverter ON/OFF switch is in the OFF position.
l
26
Single Phase Inverter with HD-Wave Technology Installation MAN-01-250-1.2
V d c [ V ]
P a c [ w ]
1 4 . 1
0 . 0
0 0 0 / 0 0 0
< S _ O K >
O F F