Installation. P9; Installation Procedure For Panel. P9 - BeaconMedaes MAT-S Installation,Operation And Maintenance Instruction

Medical gas supply system cylinder manifold system and manifold changeover system
Table of Contents

Advertisement

Medical Gas Supply System
2.
Installation.
2.1
Installation Procedure for
Panel.
CAUTION! Ensure no contaminates, oil or grease
come into contact with any of the gas connection/
internals.
2.1.1
Unpack and inspect all items for damage.
2.1.2
Check wall for suitability.
CAUTION! Supplied fixings are for use with solid
masonry walls only. Alternative fixing types are not
suppled with the unit. For securing to alternative wall
types, ensure that wall structure and selected fasteners
are suitable for supporting the 35 kg weight of the
Manifold Changeover System.
2.1.3
Identify the centre position of the manifold
System on the wall. Position the mounting bracket as
shown and mark the mounting hole positions. See
figure 3 for typical mounting heights depending on the
cylinder sizes used
Refer to installation drawing (P/N
.
4109992438) for more details
Figure 3 - Mounting Plate Installation Details.
MOUNTING HOLES
145
NOTE - Mounting height Position for 'J' size cylinders
is 859 mm and 'VF' size when using the step-down
connection pipe (see figure 5 & 6). Mounting heights for
'VF' size cylinders is 289 mm.
.
12.7(4x)
290
2.1.4
Drill wall and fit wall plugs. Screw the manifold
bracket to the wall, checking that it is firmly attached.
2.1.5
Hook the manifold panel onto the mounting
bracket as shown in figure 4. Ensure the studs line up
with the holes in the back plate, then lever down into
position. Secure the panel on to the mounting plate with
the 4 x M8 shouldered nuts.
Figure 4 - Manifold Changeover System Mounting.
9
M8
Screw
M8
Weld Nut
4 x
Mounting
Points
4109992485.00