Step 5 – Connect Open String Alarm – Some Models - Optional
Connect OS Alarm as directed in site installation instructions.
J3 1-Wire Battery
Temp Monitor
J5 LAN Port
Step 6 – Set Jumpers – LAN Port and Relay per Galaxy Pulsar Edge Controller
Quick Start Guide
Step 7 – Install Controller per Galaxy Pulsar Edge Controller Quick Start Guide
Step 8 – Install Signal and Communications Cables
Connectors are on rear.
1.
J1-2 Alarms and Inputs - Connect to office alarms and signals.
See Information: Alarm Connections for Details
2.
J5
LAN - Connect to Ethernet network.
Step 9 – Install 1-Wire Battery Temp and Voltage Monitor per Galaxy Pulsar
Edge Controller Quick Start Guide – Optional
1. Connect 1-Wire Battery Temp and Voltage Monitor to J3.
Step 10 – Install Rectifiers
Firmly push the rectifier into the rectifier slot.
Tighten the thumb screw until the rectifier is seated.
NOTE: When installing a rectifier in a powered system the RUN LED on the
rectifier will blink until communication with the controller is
established.
Page 3
2023 ABB. All rights reserved.
J2 Alarm inputs
J1 Alarm outputs
Signal Connections
SPS Shelf L002_QSG
USB Craft Port
Rev 5.0