6. Installation Checkout

Test for Leaks
Turn on the water supply to the valve.
Connect the jumper to the valve.
Verify there is power to the 120 V electrical outlet, then plug the power cord into the outlet.
Wait 10 seconds for the valve to initialize; the outlets will activate.
Check all connections for leaks.
Disconnect the power, then remove the jumper.
Connect the Cables
NOTE: Make drip loops in all cables and cords.
Install the K-99695 system controller according to the instructions packed with the product.
Route the data cable in the wall between the controller and valve installation location.
Attach a split boot to the data cable, toward the end that will connect to the valve.
Connect the cable to the valve. Press the boot over the connection in the valve socket.
Insert a solid boot into the unused socket.
Configure the Valve (Requires an Installed Controller)
NOTE: Valves which have been recently installed, or have not been used for some time should be
exercised before running tests or setting the maximum temperature.
To configure valve setup, refer to the guide on the K-99695 controller product page at
www.us.kohler.com.
Before Operating the System For the First Time:
Download and install the latest software for connected components. This may take an hour or more to
complete based on system configuration and internet connection speed. Do not disconnect the power from
any components during software download and installation.
1240338-2-A
Jumper
Split
Boot
Solid Boot
10
Slide the split boot
onto the cable.
Drip Loop