Bosch IDP Premium BRBA-60HWD1N1-M18 Installation Instructions Manual page 11

Inverter ducted packaged heat pump
Table of Contents

Advertisement

Units should be elevated 3-12 inches above the pad or rooftop,
depending on local weather. This additional height will allow drainage
of snow and will permit condensate water to drain when the unit
is in defrost mode. Ensure that drain holes in unit base pan are
unobstructed, preventing drainage of defrost water (See Fig.9).
If possible, avoid locations that are prone to snow drifts. If not possible,
a snow drift barrier should be installed around the unit to prevent a
build-up of snow on the sides of the unit.
  E nsure that Condensate Drain side is pitched lower than the
opposite side.
Condensate drain side
Figure 6
Avoid Install
Near Bedrooms
Min. 24"
Access Panel
Figure 7
  A minimum clearance of 24" should be maintained adjacent to
all access/service panels. Refer to local code requirements for additional
clearance requirements.
Bosch 18 SEER2 Series Inverter Ducted Packaged Heat Pump - BTC 761703104 A (11.2022)
0
h≤ 25mm(1°)
Min. 60" Unrestricted
Min. 24"
Access Panel
Min. 24"
Access Panel
Figure 8
Min 24"
Snow
barrier
Figure 9
Corrosive Environment
Exposure to a corrosive environment may shorten the life of the equipment,
corrode metal parts, and/or negatively aff ect unit performance. Corrosive elements
include, but are not limited to: sodium chloride, sodium hydroxide, sodium sulfate,
and other compounds commonly found in ocean water, sulfur, chlorine, fl uorine,
fertilizers, and various chemical contaminants from industry/manufacturing plants.
If installed in areas which may exposed to corrosive environments, special
attention should be given to the equipment placement and maintenance.
Lawn sprinklers/hoses/waste water should not spray directly on the
unit cabinet for prolonged periods of time.
In coastal areas: locate the unit on the side of the building or roof away
from the waterfront.
Fencing or shrubbery may provide some shielding protection to the
unit, however minimum unit clearances must still be maintained.
Every three months, wash the outdoor coil and any exposed cabinet
surfaces.
Installation Instructions
Min. 12" to
Shrubbery
Supply Air Duct
Snow legs
3- 12" Elevation
pad
| 11

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents