Charging The Unit; Control Board Navigation Components; Gas Heat Stages; Typical Gas Valve - York ZJ150 Installation Manual

Hide thumbs Also See for ZJ150:
Table of Contents

Advertisement

1183875-YIM-A-1014
Table 28: Gas Heat Stages
# of Burner Tubes
4
6
8
Adjustment Of Temperature Rise
The temperature rise (the difference of temperature between the
return air and the heated air from the furnace) must lie within the
range shown on the CSA rating plate and the data in Table 9.
After the temperature rise has been determined, the CFM can
be calculated as follows:
After about 20 minutes of operation, determine the furnace
temperature rise. Take readings of both the return air and the
heated air in the ducts (about 6 feet from the furnace) where
they will not be affected by radiant heat. Increase the blower
CFM to decrease the temperature rise; decrease the blower
CFM to increase the rise (See SUPPLY AIR DRIVE
ADJUSTMENT).
NOTE: Each gas heat exchanger size has a minimum
allowable CFM. Below this CFM, the limit will open.
Burners/Orifices Inspection/Servicing
Before checking or changing burners, pilot or orifices, CLOSE
MAIN MANUAL SHUT-OFF VALVE AND SHUT OFF ALL
POWER TO THE UNIT.
1.
Open the union fitting just upstream of the unit gas valve
and downstream from the main manual shut-off valve in
the gas supply line.
2.
Remove the screws holding each end of the manifold to the
manifold supports.
3.
Disconnect wiring to the gas valves and spark igniter's.
Remove the manifold & gas valve assembly. Orifices can
now be inspected and/or replaced.
To service burners, complete step 4.
4.
Remove the heat shield on top of the manifold supports.
Burners are now accessible for inspection and/or
replacement.
NOTE: Reverse the above procedure to replace the
assemblies.
Make sure that burners are level and seat at the rear of the gas
orifice.
60
2nd Stage Input
1st Stage Input
(100% Btuh)
(60% Btuh)
120,000
72,000
180,000
108,000
240,000
144,000
GAS
SUPPLY
PIPE
BURNER
BURNER BRACKET
IGNITOR
Figure 32: Typical Flame
HIGH & LOW GAS ADJUSTMENT
HI
INLET
PRESSURE
TAP
MATE-N-LOCK
CONNECTORS
Figure 33: Typical Gas Valve

Charging The Unit

All ZJ units use Thermal Expansion Devices. Charge the unit to
nameplate charge or 10° subcooling.

Control Board Navigation Components

The following components are needed to access the control
points in the Simplicity® SE control. Installation and operation
guides are located on www.upgnet.com under Product Center \
Equipment Catalog \ Commercial Products \ Zoning Systems
and Controls.
1.
Local LCD on Unit Control Board.
2.
Mobile Access Portal (MAP) Gateway (Portable).
• Source 1 P/N S1-JC-MAP1810-OP
3.
MAP Gateway Quick Start Guide P/N 24-10737-16
4.
MAP Gateway Instruction P/N 24-10737-8
NOTE: For more in-depth sequence of operation of the
Simplicity® SE control please refer to LIT-12011950 on
www.upgnet.com under Product Center \ Equipment
Catalog \ Commercial Products \ Zoning Systems and
Controls.
HEAT EXCHANGER TUBE
BURNER FLAME
(BLUE ONLY)
LO
ON
OFF
OUTLET
PRESSURE
TAP
MV
C
HI
Johnson Controls Unitary Products

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Zj seriesZj120Zj102Zj090Zj078Zj078-150

Table of Contents