www.cppumps.com
WARNING:
Ensure that you are wearing proper PPE before performing any action.
This document applies to vertical and horizontal motor orientations.
Tool Requirements
Open-End Wrenches: Sizes required will depend on motor frame
•
1/8" Hex Key
•
Pump Mounting
1.
Unpack Series SLA pump assembly, and ensure all ordered components are
supplied. Fastener hardware not included. Motor sold separately.
QTY
1
1
2.
Place pump onto level mounting surface. The head should always be horizontal
relative to ground with the discharge check valve vertical facing up. See Figure 1.
3.
Secure pump to stable structure to avoid tipping, using four (4) holes on outer
edge of standard foot mount. See Figure 2.
Motor Attachment
4.
The Series SLA drive is designed to support up to an 85lbf (378N)
motor.
5.
Install coupling hub with key to motor shaft and tighten the set
screw.
6.
Align the motor side coupling with the factory Series SLA coupling
hub, with the elastomer spider inserted.
7.
Align the motor flange with the Series SLA adapter flange and secure
by installing four (4) bolts (not included) sized according to the motor
frame.
8.
Connect motor to electrical service with overcurrent protection and
means to safely interrupt power, following local rules and
regulations.
CP/DWG-ENG-006
REV. 01
DESCRIPTION
SERIES SLA PUMP
SHAFT COUPLING HUB + SPIDER
EFF. DATE: 01/11/2023
QUICK SETUP
Series SLA LeakLess
/
Figure 1
Figure 2
Page 1 of 2
Need help?
Do you have a question about the SLA Series and is the answer not in the manual?
Questions and answers