Kohler ADAGIO K-731T Installation Instructions Manual page 5

Advertisement

A1.
A2. Through the Floor Drain Bath
Installation
Slide the new bath into position to verify the drain
location and the stud fit. Cut a minimum 152 x 305 mm
hole in the floor for the drain connection.
A2.
152 305mm
Use 25~30 Kg dry cement and sand mix. Add water to
make a paste mortar. Remove the tub. Cover the
installation area with the mortar starting from the middle
of the tub as shown. The height of the mortar should
reach the bottom of the rub.
NOTE:
DO NOT CLOG THE DRAIN HOLE.
Place the tub onto the mortar. Insert the drain tailpiece
into the trap.
Make sure that the bottom of the tub is pressed into
mortar in order to secure the tub. Insert two wood
wedges under the tub to support the weight of the tub
until the mortar hardens. (Wedges will remain in the
mortar.) Frequently check the level of the tub.
25~30
1006291-T01-C
Metal Shim
Drain Hole
-5-
Brick
Level
Paste Mortar
Wood Wedge
Middle of Bath