Move to desired location
If
If machine can be
moved without
adding or removing
weight stacks.
If
If machine needs
weight stacks
removed before
moving to desired
location.
If
If machine needs
weight stacks
removed before
moving to desired
location.
Move to machine to the desired location
1. Remove the four shipping cones using a 3/4" socket or wrench.
2. Attach foot pads to each foot of frame.
Cybex Owner's Manual
Two people will be required for this procedure
1. Move to desired location.
2. Remove the four shipping cones using a 3/4" socket or wrench.
3. Attach foot pads to each foot of frame.
Two people will be required for this procedure
1. Do not remove middle BHSCS securing shroud to bottom bracket
2. Remove the two Button Head Socket Cap Screws (BHSCS)
securing the bottom bracket to the frame sing a 1/8" Allen wrench.
3. Remove the remaining BHSCS securing the back shroud to the
frame.
4. After the final BHSCS is removed shroud will slide down to the
floor with bottom bracket attached.
5. Slide shroud out of machine.
6. Slide spring loaded top guide rod cap down guide rod until cap is
clear of frame.
7. Slowly release grasp of guide rod cap.
8. Guide rod cap contains a compression spring that will fly if grasp
is not released slowly.
9. Remove
guide rod cap and spring and set aside.
10. Repeat above steps for opposite guide rod.
11. Lean guide rods slightly outward, away from machine to clear
pulley. DO NOT put excessive pressure on guide rods, it will
damage rod caps
12. Slide top weight up and out of the machine and set aside.