9.10.1.1

Testing permissive underreaching

1.
Activate the receive (CR) signal in the IED.
2.
Apply healthy normal load conditions to the IED for at least two seconds.
3.
Apply a fault condition within the permissive zone.
4.
Check that correct trip outputs, external signals, and indications are obtained for the
actual type of fault generated.
5.
Check that other zones operate according to their zone timers and that the send (CS)
signal is obtained only for the zone configured to generate the actual signal.
6.
Deactivate the receive (CR) signal in the IED.
7.
Check that the trip time complies with the zone timers and that correct trip outputs,
external signals, and indications are obtained for the actual type of fault generated.
9.10.1.2

Testing permissive overreaching

1.
Activate the receive (CR) signal in the IED.
2.
Apply healthy normal load conditions to the IED for at least two seconds.
3.
Apply a fault condition within the permissive zone.
4.
Check that correct trip outputs, external signals, and indication are obtained for the
actual type of fault generated.
5.
Check that the other zones operate according to their zone timer and that the send (CS)
signal is obtained only for the zones that are configured to give the actual signal. Also the
zone connected to CS underreach is giving CS in this mode.
6.
Deactivate the IED receive (CR) signal.
7.
Apply healthy normal load conditions to the IED for at least two seconds.
8.
Apply a fault condition within the permissive zone.
9.
Check that trip time complies with the zone timers and that correct trip outputs, external
signals, and indications are obtained for the actual type of fault generated.
9.10.1.3

Testing blocking scheme

1.
Deactivate the receive (CR) signal of the IED.
2.
Apply healthy normal load conditions to the IED for at least two seconds.
3.
Apply a fault condition within the forward directed zone used for scheme communication
tripping.
4.
Check that correct trip outputs and external signals are obtained for the type of fault
generated and that the operate time complies with the
measuring time).
5.
Check that the other zones operate according to their zone times and that a send (CS)
signal is only obtained for the reverse zone.
6.
Activate the IED receive (CR) signal.
7.
Apply a fault condition in the forward directed zone used for scheme communication
tripping.
8.
Check that the no trip from scheme communication occurs.
9.
Check that the trip time from the forward directed zone used for scheme communication
tripping complies with the zone timer and that correct trip outputs, external signals, and
indications are obtained for the actual type of fault generated.
9.10.1.4

Testing delta blocking scheme

Line differential protection RED650
Commissioning manual
© Copyright 2017 ABB. All rights reserved
Testing functionality by secondary injection
tCoord timer (plus relay
GUID-D5FF46AF-0C5A-4AD4-8F2C-09EC17B681F1 v2
Section 9
M13868-10 v4
M13868-28 v4
M13868-50 v5
105

Advertisement

Table of Contents
loading

This manual is also suitable for:

Relion red650

Table of Contents