4.
Inject the measured voltages at rated values for at least set
5.
Activate the CBOPEN binary input.
6.
Simultaneously disconnect all the three-phase voltages from the IED.
No TRIP signal should appear.
7.
Inject the measured voltages at rated values for at least set
8.
Activate the VTSU binary input.
9.
Simultaneously disconnect all the three-phase voltages from the IED.
No TRIP signal should appear.
10.
Reset the VTSU binary input.
11.
Inject the measured voltages at rated values for at least set
12.
Activate the BLOCK binary input.
13.
Simultaneously disconnect all the three-phase voltages from the IED.
No TRIP signal should appear.
14.
Reset the BLOCK binary input.
9.4.4.2

Completing the test

continue to test another function or end the test by changing the
Restore connections and settings to their original values, if they were changed for testing
purposes.
9.5

Secondary system supervision

9.5.1

Current circuit supervision CCSSPVC

Prepare the IED for verification of settings outlined in Section
settings".
The Current circuit supervision function CCSSPVC is conveniently tested with the same three-
phase test set as used when testing the measuring functions in the IED.
The condition for this procedure is that the setting of
Ip>Block .
9.5.1.1

Verifying the settings

1.
Check the input circuits and the operate value of the
injecting current, one phase at a time.
2.
Check the phase current blocking function for all three phases by injecting current, one
phase at a time. The output signals shall reset with a delay of 1 second when the current
exceeds 1.5 ·
3.
Inject a current 0.1 ·
4.
Increase slowly the current in one of the phases and check that FAIL output is obtained
when the current is above 0.9 ·
9.5.1.2
Completing the test
continue to test another function or end the test by changing the
Restore connections and settings to their original values, if they were changed for testing
purposes.
Breaker protection REQ650
Commissioning manual
Note that TRIP at this time is a pulse signal, duration should be according
tPulse .
to set
IBase .
IBase to the reference current input I5.
IBase .
© Copyright 2017 ABB. All rights reserved
Testing functionality by secondary injection
tRestore time.
tRestore time.
tRestore time.
TESTMODE setting to Off .
"Preparing the IED to verify
IMinOp is lower than the setting of
IMinOp current level detector by
TESTMODE setting to Off .
Section 9
SEMOD175023-47 v4
SEMOD53556-1 v1
M12917-25 v8
M12917-31 v8
M12917-43 v4
75

Advertisement

Table of Contents
loading

This manual is also suitable for:

Relion req650

Table of Contents