Checklist During Commissioning; Minimum Flow Rate - Daikin ERGA04EAV37 Installer's Reference Manual

Hide thumbs Also See for ERGA04EAV37:
Table of Contents

Advertisement

12
|
Commissioning

12.4 Checklist during commissioning

12.4.1 Minimum flow rate

Installer reference guide
244
The power supply voltage matches the voltage on the identification label of the unit.
There are NO loose connections or damaged electrical components in the switch box.
There are NO damaged components or squeezed pipes on the inside of the indoor and
outdoor units.
Backup heater circuit breaker F1B (field supply) is turned ON.
There are NO refrigerant leaks.
The refrigerant pipes (gas and liquid) are thermally insulated.
The correct pipe size is installed and the pipes are properly insulated.
There is NO water leak inside the indoor unit. All electric components and connections are
dry.
The shut-off valves are properly installed and fully open.
The automatic air purge valves are open.
The pressure relief valve purges water when opened. Clean water MUST come out.
The minimum water volume is guaranteed in all conditions. See "To check the water
volume and flow rate" in
The storage tank is filled completely.
The minimum flow rate during backup heater/defrost operation is guaranteed in all
conditions. See "To check the water volume and flow rate" in
4
piping" [
 101].
To perform an air purge.
To perform a test run.
To perform an actuator test run.
Underfloor screed dryout function
The underfloor screed dryout function is started (if necessary).
To set up a bivalent heat source.
Purpose
For a correct operating unit, it is important to check if the minimum flow rate is
reached. If needed, modify the bypass valve setting.
Minimum required flow rate
12 l/min
To check the minimum flow rate
1 Check the hydraulic configuration to find out which space
heating loops can be closed by mechanical, electronic, or other
valves.
"8.5 Preparing water
piping" [
ERGA04~08EAV3+V3A+V37 + EHSH/X(B)04+08P30+50EF
4
 101].
"8.5  Preparing water
Daikin Altherma 3 R ECH₂O
4P678716-1A – 2022.07

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents