D-Link DCS-9200T Quick Installation Manual page 6

Group temperature screening camera kit
Table of Contents

Advertisement

Ceiling Mount Configuration (Optional)
2 - 2.3 m
5 m
1.
If mounting from the ceiling, the DCS-9200T should be installed anywhere from 2-2.3 m from the
ground.
The Blackbody should be installed at the same height as the camera, but 3-5 m from the camera,
2.
inside the field of view (FOV) of the camera. The optimal distance to measure temperature is at
the same distance as the blackbody is installed.
4
3 - 5 m (4 m recommended)
3 m
DCS-9200T Quick Installation Guide
2 - 2.3 m