ABB RELION 650 Series Commissioning Manual page 61

Transformer protection
Hide thumbs Also See for RELION 650 Series:
Table of Contents

Advertisement

1MRK 504 160-UEN A
1.
Right click on the IED in the plant structure and select
2.
Click on the
3.
Click
IEC15000023 V1 EN-US
4.
Click
IEC15000024 V1 EN-US
The Signal Monitoring menu changes and indicates the forcing values that can be edited.
IEC15000025 V1 EN-US
5.
Select and edit the values.
6.
Click
IEC15000026 V1 EN-US
This commits the values to the IED and exits the editing session.
7.
Click
IEC15000032 V1 EN-US
Commissioning manual
List View tab.
Forcing Session in the menu IED/Start Forcing .
Start editing signal value for forcing on the tool bar.
Acknowledge and send .
Cancel to abort the changes and revert back to actual IED values.
Testing IED operation
Signal Monitoring.
Section 9