Figure 5-26 Connecting the cable
Step 2 Connect the signal cable connector to the COM port.
Figure 5-27 Securing the signal cable connector
----End
5.7.4 (Optional) Connecting the Power Grid Scheduling Signal
Cable
Procedure
Step 1 Connect the signal cable to the signal cable connector.