Sealing Cabinet To The Floor - True TFP-72-30M-D-2 Installation Manual

Undercounters worktops sandwich/salad pizza prep & food prep
Hide thumbs Also See for TFP-72-30M-D-2:
Table of Contents

Advertisement

TRUE
refrigerated prep
INSTALLATION OF CASTORS OR OPTIONAL LEGS
(TFP MODELS ONLY)
ADJUSTING CASTORS FOR PROPER LEVELING
Level unit. If unit is not level shims are required. Follow these instruc-
tions to install shims.
A. Remove front and rear grill depending upon which castor
needs adjusting. Locate the castor box.
B.
Lay unit on it's back. Use soft packing material and be careful
not to scratch the unit. Remove pans and lid and place them
to the side before laying unit on it's back.
C. Each unit has one castor box different from the others. This
box is totally enclosed. Remove this castor box from bottom
of unit. Back out four screws anchoring the box. You will need
a 1/4" hex head nut driver to disassemble this castor box.
D. Loosen castor with tool provided.
E.
Install the desired number of shims, making sure the slot of the
shim is in contact with the threaded stem of the castor. If more
than one shim is used, turn the slot at a 90° angle so they are
not in line.
F.
After adjusting castor reassemble and reinstall castor box.
Then carefully upright unit and reinstall pans and lid. Angle so
they are not in line.
Leveling Shim
Leg
roller box
anchoring
1
screw
Locate castor box
3
Loosen castor.
Bearing
Race
Castor
2
One castor box on each unit is fully
enclosed.
4
Install shims.
SEALING CABINET TO FLOOR
STEP 1 - Position Cabinet - Allow one inch between the wall and
rear of the refrigerator to assure proper ventilation. For freezers 3
inches between the wall and rear of the cabinet will assure proper
ventilation.
STEP 2 - Level Cabinet - Cabinet should be level, side to side and
front to back. Place a carpenter's level in the interior floor in four
places:
A. Position level in the inside floor of the unit near the doors.
(Level should be parallel to cabinet front). Level cabinet.
B.
Position level at the inside rear of cabinet. (Again level should
be placed parallel to cabinet back).
C. Perform similar procedures to steps A & B by placing the level
on inside floor (left and right sides - parallel to the depth of the
cooler). Level cabinet.
STEP 3 - Draw an outline on the base on the floor.
STEP 4 - Raise and block the front side of the cabinet.
STEP 5 - Apply a bead of "NSF Approved Sealant", (see list below),
to floor on half inch inside the outline drawn. The bead must be heavy
enough to seal the entire cabinet surface when it is down on the
sealant.
STEP 6 - Raise and block the rear of the cabinet
STEP 7 - Apply sealant on floor as outlined in Step 5 on other
three sides.
STEP 8 - Examine to see that cabinet is sealed to floor around
entire perimeter.
NOTE: Asphalt floors are very susceptible to chemical attack. A
layer of tape on the floor prior to applying the sealant will protect
the floor.
NSF APPROVED SEALANTS:
1. Minnesota Mining #ECU800 Caulk
2. Minnesota Mining #ECU2185 Caulk
3. Minnesota Mining #ECU1055 Bead
4. Minnesota Mining #ECU1202 Bead
5. Armstrong Cork - Rubber Caulk
6. Products Research Co. #5000 Rubber Caulk
7. G.E. Silicone Sealer
8. Dow Corning Silicone Sealer
.
.
www
truemfg
com
6

Advertisement

Table of Contents
loading

This manual is also suitable for:

Tpp-67Tssu-48-10Twt-67d-2Tuc-67-hc

Table of Contents