Start-Up

Preliminary and Seasonal Checks
1.
Inspect electrical wiring, both field and factory installed
for loose connections. Tighten as required.
2.
Check voltage at disconnect switch. Voltage must be
within range listed on the nameplate. If not, consult the
power company and have voltage condition corrected
before starting unit.
3.
Inspect condition of condensate traps and drain
assembly. Disassemble and clean seasonally.
Heating Start-Up
BEFORE LIGHTING the unit, smell all around the furnace
area for gas. Be sure to smell next to the floor because some
gas is heavier than air and will settle on the floor.
The gas valve on the NF96DS is equipped with a gas control
switch. Use only your hand to move the switch. Never use
tools. If the the switch will not move by hand, replace the
valve. Do not try to repair it. Force or attempted repair may
result in a fire or explosion.
Placing the Furnace Into Operation
NF96DS units are equipped with an ignition system. Do not
attempt to manually light burners on this furnace. Each time
the thermostat calls for heat, the burners will automatically
light. The ignitor does not get hot when there is no call for
heat on units with ignition system.
Priming Condensate Trap
The condensate trap should be primed with water prior to
start-up to ensure proper condensate drainage. Either pour
10 fl. oz. (300 ml) of water into the trap, or follow these steps
to prime the trap:
1. Follow the lighting instructions to place the unit into
operation.
2.
Set the thermostat to initiate a heating demand.
3.
Allow the burners to fire for approximately 3 minutes.
4.
Adjust the thermostat to deactivate the heating demand.
5.
Wait for the combustion air inducer to stop. Set the
thermostat to initiate a heating demand and again allow
the burners to fire for approximately 3 minutes.
6.
Adjust the thermostat to deactivate the heating demand
and again wait for the combustion air inducer to stop. At
this point, the trap should be primed with sufficient water
to ensure proper condensate drain operation.
If you do not follow these instructions exactly, a fire
or explosion may result causing property damage,
personal injury or death.
Gas Valve Operation (Figure 49)
1. STOP! Read the safety information at the beginning of
this section.
2.
Set the thermostat to the lowest setting.
3.
Turn off all electrical power to the unit.
4.
This furnace is equipped with an ignition device which
automatically lights the burners. Do not try to light the
burners by hand.
5.
Remove the access panel.
6.
Move gas valve switch to OFF. See Figure 49.
7.
Wait five minutes to clear out any gas. If you then smell
gas, STOP! Immediately call your gas supplier from a
neighbor's phone. Follow the gas supplier's instructions.
If you do not smell gas go to next step.
8.
Move gas valve switch to ON. See Figure 49.
MANIFOLD PRESSURE
ADJUSTMENT SCREW
(under barbed fitting)
INLET
PRESSURE
PORT
GAS VALVE SHOWN IN ON POSITION
Figure 49. Gas Valve
9.
Replace the access panel.
10. Turn on all electrical power to to the unit.
11. Set the thermostat to desired setting.
NOTE: When unit is initially started, steps 1 through 11
may need to be repeated to purge air from gas line.
12. If the appliance will not operate, follow the instructions
"Turning Off Gas to Unit" and call your service technician
or gas supplier.
Turning Off Gas to Unit
1. Set the thermostat to the lowest setting.
2.
Turn off all electrical power to the unit if service is to be
performed.
3.
Remove the access panel.
Page 42
WARNING
MANIFOLD
PRESSURE
OUTLET
PORT
31-5000729 Rev. 0

Advertisement

Table of Contents
loading

This manual is also suitable for:

Ge nf96d045s3bGe nf96d070s4bGe nf96d090s4c

Table of Contents