Initial Storage And/Or Idle Period Recommendations - EVAPCO ATC-E Operation And Maintenance Instruction

Table of Contents

Advertisement

Containerized Product Lines
• CATWB - Closed Circuit Cooler
• CATC - Evaporative Condenser
WDW – Wet/Dry Closed Circuit Cooler
eco Product Line
• eco-ATW - Closed Circuit Cooler
• eco-ATWE - Wet/Dry Closed Circuit Cooler
• eco-ATC - Wet/Dry Evaporative Condenser
Forced Draft equipment includes the following Evapco Product Models:
LR Product Lines
• LRWB - Closed Circuit Cooler
• LRC - Evaporative Condenser
LS Product Lines
• LSWE - Closed Circuit Cooler
• LSC-E - Evaporative Condenser
PM Product lines
• PMC-E - Evaporative Condenser
• PMC-EQ - Evaporative Condenser
• PMWQ - Closed Circuit Cooler

Initial Storage and/or Idle Period Recommendations

If the unit will sit for idle periods of time it is recommended that the following be performed in addition to all component
manufacturers recommended maintenance instructions.
The fan/motor/pump bearings and motor bearings need to be turned by hand at least once a month. This can be
accomplished by tagging and locking out the unitʼs disconnect, grasping the fan assembly (or removing the pump motor fan
guard), and rotating it several turns.
If unit sits longer than a few weeks, run gear reducer (if equipped) for 5 minutes weekly.
If unit sits longer than 3 weeks, completely fill gear reducer with oil. Drain to normal level prior to running.
If unit sits longer than one month, insulation test motor windings semi-annually.
If fan motor sits idle for at least 24 hours while the spray pumps are energized distributing water over the coil, motor space
heaters (if equipped) should be energized. Alternatively, fan motors may be energized for 10 minutes, twice daily, to drive any
moisture condensation out of the motor windings.
Operation and Maintenance Instructions