Procedure
Step 1 Route the cables through the junction box and prepare cable terminals.
● Before routing cables, check that the sealing strips of the connection box are
● The cable stripping length must meet the requirements. Otherwise, the
● The OT terminal size must match the cross-sectional area of the AC output
Figure 5-8 Routing cables
Inner Diameter
15 mm
22 mm
26 mm
6 mm
8.6 mm
11 mm
Step 2 Install AC output power cables and signal cables. (The following uses the RS485
signal cables as an example. For details about other signal cables, see the signal
definitions of communications ports.)
Issue 03 (2023-02-15)
NO TICE
intact. Otherwise, the airtightness and waterproof performance of the device
may be affected.
airtightness and waterproof performance of the device may be affected.
power cable and M5 screw specifications.
Copyright © Huawei Digital Power Technologies Co., Ltd.