Plan the Installation

The plan should include consideration and calculations for the following:
Clarity Matrix G3 LCD Video Wall System Installation Guide
020-1339-00H
• Floor/wall load: Make sure the structure that the product will be attached to is
able to safely support the weight of the whole video wall. See "Specifications"
on page 149 for component weight(s).
• Ventilation and cooling requirements: For passive cooling, we recommend a
minimum of 200mm (8") of top and bottom clearance. Please consult Planar
Sales for video walls that are more than eight LCD Displays high. It is very
important that there is proper cooling and ventilation for the entire video wall
and its remotely-located equipment. Ventilation requirements can be reduced if
the video wall is actively cooled.
• Power consumption: Plan the building power appropriately for the video wall
power consumption. Refer to "Calculating DC Power Requirements and
Component Heat Load" on page 47 for more information.
• Cable routing to the video wall: To help the installation run more smoothly, it
is highly recommended that a cabling diagram of primary and interconnecting
cables be created, including power, source and control, prior to installation. This
should account for how long cable runs need to be and where they will be
routed as well as compliance with all local building codes and local, state and
federal laws.