Preparations
(Optional) Replacing a U Space E-Label
1.
2.
(Optional) Replacing an Asset Detection Strip
1.
2.
3.
4.
5.
(Optional) Replacing a Main Control Box
1.
2.
3.
4.
Issue 02 (2022-07-30)
Tools: ESD gloves, label, marker
Material: smart U space manager
Remove the faulty U space e-label from the customer equipment and the
asset detection strip.
Record the asset according to the commissioning guide.
Label the position of each U space e-label on the asset detection strip.
Remove all U space e-labels from the asset detection strip.
Remove the faulty asset detection strip.
Install a new asset detection strip in the original position.
Install the U space e-labels in the original positions based on the position
labels.
Label each cable based on the corresponding ports on the main control box.
Remove the faulty main control box.
Install a new main control box in the original position.
Connect the cables to the new main control box based on the cable labels.
Copyright © Huawei Digital Power Technologies Co., Ltd.
5 Parts Replacement
125

Advertisement

Table of Contents
loading

This manual is also suitable for:

V100r022c10

Table of Contents