Riello RDB1R GRANT MILTON 20 kW Installation, Use And Maintenance Instructions page 14

Light oil burner
Hide thumbs Also See for RDB1R GRANT MILTON 20 kW:
Table of Contents

Advertisement

On the systems in Fig. 13 and Fig. 14 start the burner and wait
for the priming.
Should lock-out occur prior to the arrival of the fuel, await at least
20 seconds before repeating the operation.
In order to purging air from oil lines and filters re-
peat for maximum 5 times the complete operation
programme, to protect the pump.
The pump suction should not exceed a maximum
WARNING
of 0.4 bar (30 cm Hg). Beyond this limit gas is re-
leased from the oil. Oil pipes must be completely
tight.
D1842
H
metres
0
0.5
1
1.5
2
3
3.5
H
difference of level
L
maximum length of the suction line
Ø
internal diameter of the oil pipes
20166849
60 µm
60 µm
L metres
Ø (8 mm)
Ø (10 mm)
35
100
30
100
25
100
20
90
15
70
8
30
6
20
Installation
In the vacuum systems (Fig. 14) the return line should terminate
within the oil tank at the same level as the suction line. In this
case a non-return valve is not required. Should however the re-
turn line arrive over the fuel level, a non-return valve is required.
This solution however is less safe than previous one, due to the
possibility of leakage of the valve.
D5740
NOTE:
In case of digital applications the priming pump is possible
not only with the previous procedure but also with a specific
function implemented into the digital control box (see 4.7.9,
page 10). In this case the priming pump time could be longer.
Fig. 13
Tab. E
12
GB
60 µm
Fig. 14